The videos below illustrate the assembly speed of Quad-Lock's Insulating Concrete Forms.
The experienced crew on this ICF project finished the formwork for a full basement and garage in one day. The concrete was successfully poured the next morning in a few hours. The metal track was attached to the footing the previous day in a few hours. Though barely visible in this time-lapse, corner brackets and rebar were installed.
Note that inexperienced crews will take longer for the first few projects but usually achieve 'experienced' speed after just two projects.
Special Thanks to Homes American Made Co. (Quad-Lock Distributor in Michigan)!
Note: the camera moved in the middle for the concrete pour of the foundation and addition of the pool.
Special Thanks to Better Concept Builders Ltd. for the above!